Branch Settings Schedule - Contractor

Modified on Thu, 13 Nov at 4:53 PM

The Branch Schedule Settings screen contains multiple sub-tabs where you can customise certain aspects of your Schedule settings.

 

Branch Schedule Settings Permissions

You can manage permissions for Branch Schedule Settings from your Profile drop-down menu with the manage users permission.

  1. Go to Branch SettingsManage Users.

  2. Select the user whose permissions you want to edit.

  3. Click Edit, then scroll down to the Branch Settings section.

In this section, you’ll see five permission options. For each option, you can assign one of the following access levels:

  • No Access, View Only or Full Permission (Edit)

  • Branch Owners have Full Access by default. Other tier 1 Users can be granted optional access except Site Manager.


You can access your branch Schedule Settings, with permission, via your profile drop-down icon - the teal coloured circle with your initials to the top right of your page.  

Clicking on this icon, scroll down to Branch Settings | Schedule Settings option.  

Clicking on this page opens your Schedule Settings screen.


The section is broken down into General, Holidays, Contractor, Replace Assignee and Schedule Mode. 


This article will focus on the Contractor Sub tab



Managing Your Schedule’s Contractor Settings

You can configure your contractors’ task completion and acceptance processes to suit your scheduling workflow.


Allow Contractor to view Task AssigneeOnce enabled the contractors can see who else is assigned to tasks on the same project.

Task Acceptance Notifications - Once enabled Rave will send email notifications when contractors accept or sign off on tasks


Request Sign-Off on Tasks

The ‘Request Sign-Off on Tasks’ option allows contractors to notify you when they have completed their assigned tasks.
If this checkbox is not ticked, contractors will not be able to indicate task completion, and you will not receive completion notifications.


Accept or Decline Tasks / Propose New Start Dates

These options are available for Advanced and Enterprise Scheduling users.
They allow contractors (trades) to:

  • Accept or decline assigned tasks based on their availability

  • Propose new start dates if they are unable to complete the task on the originally scheduled days

This feature helps improve communication and ensures schedule accuracy.


Task Contractor Messages

The ‘Task Contractor Messages’ setting allows you to customise the messages displayed to contractors when they accept a Task or request sign-off for tasks.
These messages can include important reminders such as health and safety requirements or other relevant project information.


Our previous Article is on Branch Holiday Schedule Settings is here. 

Our next Article is on Branch  Replace Assignee is here.



Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article