The Quotes sub-tab is where we manage our quotes or raw costs (pricing excluding any margin). Many of our clients (and our clients' suppliers) use a QS service or Excel spreadsheets to formulate their pricing. With RAVE's CSV file upload process, you can quickly upload one or more quotes and prices into your job.
You can access your Project’s financial workflows from either the Financial button or the Project button's Project list, clicking on the project’s reference number, and finally selecting the Budget sub-tab, then Quotes.
How to Add a Quote(s) from a CSV File
To upload a quote(s) or project pricing into RAVE, go to your project's ‘Quote’ sub-tab:
- Click on the CSV Import button, to the top right of your screen
- Then, via the Upload CSV pop-up, download our example file


- Check that your suppliers (or your internal pricing) CSV file matches the example file for both column names and data, and if not, make the necessary changes to the file
Note: The CSV file headers must match the CSV example file for a successful upload- The Quote Name - is the quote reference number. You can either use the supplier or contractor's quote reference or use something easily identifiable like 'Plumbing' or 'Building Labour'
- The Company Name field must exactly match the name you have stored in Rave under the Contractor or Supplier company name field. If you are using Xero as well you must ensure that Rave and Xero also match exactly i.e. if the Company Name is 'Rave Build Management Limited' you must type the entire name in for it to match. If you are unsure who is supplying you with this item you can leave the company name field blank. RAVE will autofill it with your company name as a temporary placeholder and you can go and edit it later.
Note: While you can use the same CSV file to upload multiple supplier quotes, from multiple suppliers, you can not have two different companies using the SAME quote name i.e. you can not use the quote name 'building materials' for both ITM and Carters on the same quote CSV, though you could say “Building Materials ITM” and “Building Materials Carters” - The Category and Subcategory - must match your list of pre-populated categories and subcategories.
- The Product Code is only used for internal reference; this is the SKU/item code your supplier uses. This doesn’t send to Xero or go anywhere other than in RAVE.
- The (item) Description - can be a short name or as long as you need. Don’t use this field for the scope of works or inclusions /exclusions, as these can get too long.
- The Unit of Measurement can be whatever you choose to use. Rave does have a list of prepopulated ones, such as each, sum, hours, day, week etc
- The Qty can be a full number or a part of a number i.e. 1.0, 1.5, 0.45, etc
Note: You can not have a 0 (zero) Qty, all items must have a qty value greater than 0. You can however have a quantity of 1 and a price of $0.00. - Price is your COST price EXCLUDING GST and EXCLUDING MARKUP/MARGIN
- The Tax Rate is either 15 or 0 (% GST)
- The Markup is the percentage you wish to mark this item up by. If you prefer an overall job profit then you can leave this field blank and handle markup and margin on the estimate page.
- The Chart of Accounts - is your Xero chart of accounts code or whatever accounting system you use. You can just add the account code only - no wording is required.
- Once the supplier's CSV file is good to go, drag it to the 'Upload CSV' pop-up to load, and click the proceed button to continue.
A new pop-up will appear, showing that the upload went through 100%, otherwise, any errors that need fixing will be displayed in Orange and Red.
Note: An orange error lets you know that there is missing data, though this will not stop the CSV file from loading. Hovering over any of the orange caution signs will detail what the warning is for. Examples of orange errors include missing Category, Chart of Accounts, or Company Name data.
A red error will prevent an upload from continuing. Examples of red errors include a quote where the same quote name already exists, and where the pricing field is blank.
Once you have rectified any errors, resave your CSV file, and have another go at importing it.
You will now see all of the uploaded quotes on the quotes page - which you can now edit as required i.e. change suppliers, pricing, add a scope of works, etc. You can also approve any quotes, add them to the Estimate, or just leave as pending while you work on them.




Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article