Via the Site/Build / Build Overview / Task Gantt screen, you have the ability to print a multi-project Task List view of your selected projects - that is grouping each task list view of each selected schedule, one after the other.  

To print a Task List view of the select projects, from the Site/Build / Build Overview / Task Gantt screen:

  1. Click on the 3 dots action drop-down - to the right of the job number

  2. Select the Print Schedule Option

    This will open the 'Print Schedule' pop-up, from here you can
    • Decide to print with the oldest task start date first OR the oldest Finish date first i.e if I have a start date of  01/02/2024 and the next project has a start date of 05/04/2024 I would see the project with the February start date first. and same if that was for end dates. 
    • Decide whether the print out should include Completed Tasks
    • Decide whether the print out should include Hidden Tasks
    • Decide whether the print out should include  "my" Hidden Tasks
    • Decide which columns should be displayed on the print out
    • Decide whether the print out should displayed the primary assignees Company Name, Company and Person's Name, or the Person's Name only
       
  3. Then click Print to confirm

    This will create a Task List PDF of the selected schedules given all of your selections, with each project schedule being listed in order on a separate page - from here you can and allow you to print as normal.