Enterprise scheduling opens up a range of handy scheduling features that are best seen via the ‘Task Gantt’ view of our schedule.  With our project set to enterprise mode, we can see that there are a few changes on the screen.




1. Milestones (as well as tasks) are visible on the Gantt view with Enterprise scheduling.




2. Any color-coded milestones are more clearly seen on the Enterprise schedule Gantt view.


NOTE: We cannot color code tasks as this would disrupt the task status views. 





3. We can click and drag milestones via Enterprise's gantt view - this also moves their associated tasks


4. We can add milestones and tasks via Enterprise's gantt view 

  • Add milestones by clicking on the ‘+' icon to the right of the Duration column header 
  • Add a task by clicking on the '+' icon to the right of the duration of the milestones description 





5. Click and drag Undo/Redo buttons 

The Task Gantt in Enterprise Scheduling has these handy undo/redo buttons, allowing you to undo any click and drag milestone or task changes - that is in addition to the rollback function available with our classic scheduling. 


NOTE: We can undo up to 10 steps backward/forwards. However, refreshing/or moving off the page resets the memory of the undo/redo buttons.