Updating the Schedule - Moving Tasks in 'Classic' Mode via the Start Date - Task List View
We can update the schedule (move a task or tasks) via the task list view in 'Classic' scheduling mode, simply by:
- Clicking on a task's 'Start Date'
This will open a calendar pop-up - Clicking on the date you want to move this task's start date to
- Selecting one of three 'Future Task Movement' options:
- Move Only this Task - will leave the rest of the schedule where it is and just move this particular task to its new start date
- Move All Future Milestone Tasks - will move all of the tasks due to start today* and onwards (for this milestone only) and move those remaining milestone tasks forward/back that number of working days
- Move All Future Tasks - will move all of the tasks due to start today* and onwards (for the rest of the schedule) and move those tasks back a week. will take all of the tasks in the schedule from this date onwards and move those remaining scheduled tasks forward/back that number of working days
IMPORTANT NOTE: Rave does not consider the time of day when selecting 'All Future Tasks' - this means that ALL other tasks starting on this day (even tasks earlier in the Milestone, or in previous milestones) will also move.
- And finally, click the 'OK' button to confirm
If moving future milestone/scheduled tasks, you'll typically see the first task move, then any subsequent future tasks a few seconds afterward.
Updating the Schedule - Moving Tasks in 'Classic' Mode via the pencil icon - Task List View
We can also update the schedule via the edit task pop-up (pencil icon) of the task list view, by:
- Clicking on the edit task/pencil icon
This will open a Task Details pop-up - Clicking on a task's 'Planned Start Date' field
This will open a calendar drop-down - Clicking on the date you want to move this task's start date to
- Selecting one of three 'Future Task Movement' options:
- Move Only this Task
- Move All Future* Milestone Tasks
- Move All Future* Tasks
IMPORTANT NOTE: Rave does not consider the time of day when selecting 'All Future Tasks' - this means that ALL other tasks starting on this day (even tasks earlier in the Milestone, or in previous milestones) will also move.
- And finally, click the 'NEXT' button, and 'SAVE' on the next screen to confirm
Again, if moving future milestone/scheduled tasks, you'll typically see the first task move, then any subsequent future tasks a few seconds afterward.