The Timeframe Shift build overview - available via Projects | Build Overview | Timeframe Shift. This is a high-level report showing the variation of your first and last task of any locked schedules - where the lock schedule baseline has been set. Note: This is calculated as Business days
Each project is listed down the page, while across the page we display:
- The first locked task in the schedule, specifically the:
- Start Date (current)
- End Date (current)
- Duration of the Schedule in days.
- The difference or variation in start dates between original and locked (+ or - or O )
- The last locked task in the schedule, specifically the:
- Start Date (locked)
- End Date (locked)
- The new duration of the Schedule in days
- The End Difference
The sort arrow is also featured here to be able to sort by your project A-Z or Z-A, sort by start dates, end dates, duration and difference. The sort feature is available in each column
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article