he Timeframe Shift build overview - available via Site|Build / Build Overview / Timeframe Shift. This is a high-level report showing the variation of your first and last task of any locked schedules - where the lock schedule baseline has been set.

 

Each project is listed down the page, while across the page we display:

  1. The first locked task in the schedule, specifically the:
    • Start Date (current)
    • The original (locked) Start Date
    • The ‘Difference’ or variation between the two dates
  2. The last locked task in the schedule, specifically the: 
  • Start Date (current)
  • The original (locked) Start Date
  • The ‘Difference’ or variation between the two dates