The Timeframe Shift build overview - available via Projects | Build Overview | Timeframe Shift. This is a high-level report showing the variation of your first and last task of any locked schedules - where the lock schedule baseline has been set. Note: This is calculated as Business days
Each project is listed down the page, while across the page we display:
- The first locked task in the schedule, specifically the:
- Start Date (current)
- End Date (current)
- Duration of the Schedule in days.
- The difference or variation in start dates between original and locked (+ or - or O )
- The last locked task in the schedule, specifically the:
- Start Date (locked)
- End Date (locked)
- The new duration of the Schedule in days
- The End Difference
The sort arrow is also featured here to be able to sort by your project A-Z or Z-A, sort by start dates, end dates, duration and difference. The sort feature is available in each column