he Timeframe Shift build overview - available via Site|Build / Build Overview / Timeframe Shift. This is a high-level report showing the variation of your first and last task of any locked schedules - where the lock schedule baseline has been set.
Each project is listed down the page, while across the page we display:
- The first locked task in the schedule, specifically the:
- Start Date (current)
- The original (locked) Start Date
- The ‘Difference’ or variation between the two dates
- The last locked task in the schedule, specifically the:
- Start Date (current)
- The original (locked) Start Date
- The ‘Difference’ or variation between the two dates