The Timeframe Shift build overview - available via Projects | Build Overview | Timeframe Shift. This is a high-level report showing the variation of your first and last task of any locked schedules - where the lock schedule baseline has been set. Note: This is calculated as Business days

 

Each project is listed down the page, while across the page we display:

  1. The first locked task in the schedule, specifically the:
    • Start Date (current)
    • End Date (current)
    • Duration of the Schedule in days.
    • The difference or variation in start dates between original and locked (+ or - or O )
  2. The last locked task in the schedule, specifically the: 
  • Start Date (locked)
  • End Date (locked) 
  • The new duration of the Schedule in days
  • The End Difference


The sort arrow is also featured here to be able to sort by your project A-Z or Z-A, sort by start dates, end dates, duration and difference.  The sort feature is available in each column